On 5th of May, 2016 marks the day that GCI has finally done the renovation project requested by U Mobile to renovate their Network Operation Center
The renovation works stated in November 2015, GCI's installation team puts in 100% of their efforts to make this renovation works a success. GCI abides to the requirement and quality assurance standards set by U Mobile in order to deliver the project up the standards and the expectation of the Client.
9th February, 2016 - Completion of 1st Stage work acceptance.
26th February, 2016 - Completion of Monitor and Control Installation.
15th March, 2016 - U Mobile held the Migrating Open Ceremony.
and finally,
5th May, 2016 - Renovation Work for the NOC has finally completed and the work has been fully accepted by the Client.